Roads24GH0109

OFF CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS- PASSI- SAN RAFAEL- LEMERY- SARA RD- K0078+553- K0078+587, K0078+634- K0078+885, K0079+000- K0079+071, K0079+154- K0080+891, K0080+1014- K0081+219, K0080+891- K0080+1014

OFF CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS- PASSI- SAN RAFAEL- LEMERY- SARA RD- K0078+553- K0078+587, K0078+634- K0078+885, K0079+000- K0079+071, K0079+154- K0080+891, K0080+1014- K0081+219, K0080+891- K0080+1014 is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱31,657,920.00. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Pili, Ajuy, Iloilo
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0017541

₱57,657.00 · FY2024

Released to Marinduque State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱31,657,920.00

Progress

Reported complete (DPWH)

Start Date

April 8, 2024

Target End

November 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.