Roads20IF0025

TINABILAN - CADUHAAN - MASABA ROAD LEADING TO MASABA FALLS PALOMPON LEYTE

TINABILAN - CADUHAAN - MASABA ROAD LEADING TO MASABA FALLS PALOMPON LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱41,850,499.07. Status: Reported complete (DPWH). Contractor on record: A C RIVERO DEVELOPMENT CORP 5122. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0022788

₱-71,775,148.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 5122

720 projects · ₱21.4B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BRIDGE, BARANGAY TALABAN, HIMAMAYLAN CITY, NEGROS OCCIDENTAL

Region VI, Region VI

2021₱183.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS DAANG MAHARLIKA (LZ),K0356+076-K0357+377.00; K0357+406-K0357+894.00; K0357+920.00-K0358+819.00, CAMARINES NORTE 2ND LEGISLATIVE DISTRICT

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD WITH SEAWALL, BARANGAY TABA-TABA TO BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE, B

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS: JUBAN-MAGALLANES ROAD, JUBAN AND MAGALLANES, SORSOGON PROVINCE

Region V, Region V

2018₱139.7M
Reported complete (DPWH)
No sat.

CONST. OF CONCRETE ROAD - BRGY. SAN ANTONIO - CONDEZ - SAN LUIS - SAN VICENTE - FLORES ROAD LEADING

Region VI, Region VI

2017₱134.8M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CLUSTER V-I-REHABILITATION/IMPROVEMENT OF REVETMENT ALONG BARANGAY BAGACAY-PACO SECTION, BOTH SIDE

Region V, Region V

2021₱130.4M
Past target date (DPWH On-Going)
View all 720 projects →

4. Implementation

Contract Amount

₱41,850,499.07

Progress

Reported complete (DPWH)

Start Date

February 14, 2020

Target End

December 13, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.