Water Provision and Storage21MF0072

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), SAN MARTIN ES, ISULAN, SULTAN KUDARAT; SAMPAO ES, ISULAN, SULTAN KUDARAT; IMPAO ES, ISULAN, SULTAN KUDARAT; BUAL HEALTH CENTER, ISULAN, SULTAN KUDARAT; LAGANDANG DAY CARE CENTER, ISULAN, SULTAN KUDARAT;

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), SAN MARTIN ES, ISULAN, SULTAN KUDARAT; SAMPAO ES, ISULAN, SULTAN KUDARAT; IMPAO ES, ISULAN, SULTAN KUDARAT; BUAL HEALTH CENTER, ISULAN, SULTAN KUDARAT; LAGANDANG DAY CARE CENTER, ISULAN, SULTAN KUDARAT; is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱4,405,628.15. Status: Reported complete (DPWH). Contractor on record: ROBETH CONST AND DEV'T CORP FORMERLY: ROBETH GEN MDSE CONST. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,560,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control of Buayan River - Sampao Area, Lutayan, Sultan Kudarat
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱392,621,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,405,628.15

Progress

Reported complete (DPWH)

Start Date

November 28, 2022

Target End

February 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.