GAA 2025 SSP25CN0163

CONSTRUCTION OF MULTI-PURPOSE BUILDING, DIPACULAO, AURORA

CONSTRUCTION OF MULTI-PURPOSE BUILDING, DIPACULAO, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱9,701,829.11. Status: Past target date (DPWH On-Going). Contractor on record: HBT BUILDERS. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-F-25-0018341

₱14,011,464.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱9,701,829.11

Progress

Past target date (DPWH On-Going)

Start Date

May 27, 2025

Target End

November 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.