Flood Control and Drainage25CL0035

CONSTRUCTION OF REVETMENT ALONG BANCAL RIVER (DANACBUNGA SECTION), PHASE 1, BARANGAY DANACBUNGA, BOTOLAN, ZAMBALES

CONSTRUCTION OF REVETMENT ALONG BANCAL RIVER (DANACBUNGA SECTION), PHASE 1, BARANGAY DANACBUNGA, BOTOLAN, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱0.00. Status: Ongoing (DPWH-reported) (For Procurement (DPWH-reported)). Contractor on record: Contractor not linked in this database. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Riverbank Structure along Santo Tomas River (Omaya-Balingcaguing-Paite Section), San Narciso, Zambales (Phase 1)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-25-0015924

₱94,636.00 · FY2025

Released to Bukidnon State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱0.00

Progress

For Procurement (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.