Buildings and Facilities24BH0332

BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF 1-STOREY 4-CLASSROOM (W/ TOILET) SCHOOL BUILDING IN ANNAFUNAN ELEMENTARY SCHOOL, BARANGAY ANNAFUNAN, ECHAGUE, ISABELA

BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF 1-STOREY 4-CLASSROOM (W/ TOILET) SCHOOL BUILDING IN ANNAFUNAN ELEMENTARY SCHOOL, BARANGAY ANNAFUNAN, ECHAGUE, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱4,964,334.31. Status: Past target date (DPWH On-Going). Contractor on record: JWU CONST AND SUPPLY. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dammang West Flood Control Structure, Echague, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-24-0003283

₱-100,791,800.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

33 projects · ₱2.7B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING - TERTIARY ROADS - NAGUILIAN-SAN MARIANO ROAD, ISABELA

Region II, Region II

2023₱169.0M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MIT. FACI. W/IN MAJOR BASINS & PRIN. RIVERS -CONST. OF FLOOD CONT. STRUC. ALONG ARINGAY RIVER BASIN, TUBAO, LA UNION (PACKAGE 8), TUBAO, LA UNION

La Union 2nd DEO, Region I

2025₱144.7M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRU

Isabela 2nd DEO, Region II

2024₱144.7M
Reported complete (DPWH)

Construction of Slope Protection Structure for Cagayan River Basin, Magat River, Aplat Section, Package 2, Aurora, Isabela

AURORA (ISABELA), ISABELA, Region II

2024₱144.7M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PACKAGE 2, GUIBANG,

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, TALLUNGAN

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
View all 33 projects →

4. Implementation

Contract Amount

₱4,964,334.31

Progress

Past target date (DPWH On-Going)

Start Date

October 24, 2024

Target End

February 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.