Flood Control and Drainage20FL0023

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAN ISIDRO RIVER, SAN ISIDRO, STA. MAGDALENA, SORSOGON

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAN ISIDRO RIVER, SAN ISIDRO, STA. MAGDALENA, SORSOGON is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱42,100,796.15. Status: Reported complete (DPWH). Contractor on record: MUNTOPAR BUILDERS CORP 29800. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-20-0005538

₱1,060,893.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 29800

154 projects · ₱8.8B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE(MVUC) AS PER R.A. 11239-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (LZ)-K0275+000-K0276+024, K0276+510-K0277+000, K0283+000-K02

Region V, Region V

2024₱161.4M
Past target date (DPWH On-Going)
No sat.

CLUSTER X-CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-X-I: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (LZ)-K0601+240-K0602+000, K0605+414-K0606+42

Region V, Region V

2024₱153.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SORSOGON 2ND DISTRICT HOSPITAL, PHASE 3, IROSIN, SORSOGON, BRGY. BUENAVISTA, IROSIN,

Sorsogon 2nd DEO, Region V

2024₱143.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ROAD, BARANGAY BALETE TO SIT

Sorsogon DEO, Region V

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, BARANGAY SAN ANTONIO TO BARANGAY SAN RAFAEL, PRIETO DIAZ, SORSOGON PHASE 2, PR

Sorsogon 2nd DEO, Region V

2025₱142.6M
Past target date (DPWH On-Going)
No sat.

CONST OF MP BUILDING (COVERED COURT) AT BRGY. ROXAS, PADRE DIAZ, BRGY. PALALE, BULAN, BRGY. PAYAWIN,

Sorsogon 2nd DEO, Region V

2025₱142.1M
Past target date (DPWH On-Going)
View all 154 projects →

4. Implementation

Contract Amount

₱42,100,796.15

Progress

Reported complete (DPWH)

Start Date

February 19, 2020

Target End

November 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.