Flood Control and Drainage17AF0038

REPAIR/MAINTENANCE OF FLOOD CONTROL WORKS & DRAINAGE STRUCTURE, GUSING, NAG. LU

REPAIR/MAINTENANCE OF FLOOD CONTROL WORKS & DRAINAGE STRUCTURE, GUSING, NAG. LU is a DPWH-tracked public work in La Union 2nd DEO, Region I. Reported contract value: ₱8,247,089.30. Status: Reported complete (DPWH). Contractor on record: E E MADAYAG CONST 25029. Figures trace to dpwh.

La Union 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,247,089.30

Progress

Reported complete (DPWH)

Start Date

March 23, 2017

Target End

June 20, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.