Flood Control and Drainage24F00476

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF QUIDOLOG COASTAL ROAD, PHASE 1, BARANGAY QUIDOLOG, PRIETO DIAZ, SORSOGON,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF QUIDOLOG COASTAL ROAD, PHASE 1, BARANGAY QUIDOLOG, PRIETO DIAZ, SORSOGON, is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱32,960,996.10. Status: Past target date (DPWH On-Going). Contractor on record: WELEX CONST INC FORMERLY WELEX C 9323. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 9323

78 projects · ₱4.5B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF COASTAL ROAD, ZONE 6-ZONE 7, BULAN, SORSOGON, BULAN, SORSOGON (2ND

Region V, Region V

2024₱173.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF POBLACION NORTE-CENTRAL AND SUR COASTAL ROAD, BARCELONA, SORSOGON, BARCEL

Region V, Region V

2023₱173.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS(SIPAG)-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF PINONTINGAN-PANGANIBAN COASTAL ROAD, GUBAT, SORSOGON, GUBAT, SORSOGON(2ND

Region V, Region V

2023₱144.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF ZONE 7-INARAN-NASUJE COASTAL ROAD WITH SHORE PROTECTION, BULAN, SORSOGON,

Region V, Region V

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS: JCT. PUTIAO-PILAR-DONSOL ROAD, SORSOGON 1ST LEGISLATIVE DISTRICT

Region V, Region V

2018₱139.7M
Reported complete (DPWH)
No sat.

MFO1-NATIONAL ROAD NETWORK SERVICES IMPROVEMENT/WIDENING OF NATIONAL ROADS, PRIMARY ROADS ALONG N1 DAANG MAHARLIKA (LZ), K0605+527-K0610+100 WITH EXCEPTIONS, SORSOGON

Region V, Region V

2017₱114.8M
Reported complete (DPWH)
View all 78 projects →

4. Implementation

Contract Amount

₱32,960,996.10

Progress

Past target date (DPWH On-Going)

Start Date

January 10, 2025

Target End

July 10, 2025

5. Audit