Buildings and Facilities16FB0153

REHABILITATION/REPAIR/IMPROVEMENT/RESTORATION/UPGRADING OF CAMALIG MHO

REHABILITATION/REPAIR/IMPROVEMENT/RESTORATION/UPGRADING OF CAMALIG MHO is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱8,295,263.58. Status: Reported complete (DPWH). Contractor on record: 9LEAVES BUILDERS. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱19,778,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of Flood Control System along Lava Gully (Left Side) at Mabinit River, Legazpi City, Albay
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0035504

₱259,000.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱8,295,263.58

Progress

Reported complete (DPWH)

Start Date

January 9, 2018

Target End

May 8, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.