Buildings and Facilities17GB0028

CONSTRUCTION OF 2 CLASSROOM ELEMENTARY SCHOOL, IGBANGCAL, TOBIAS FORNIER, ANTIQUE

CONSTRUCTION OF 2 CLASSROOM ELEMENTARY SCHOOL, IGBANGCAL, TOBIAS FORNIER, ANTIQUE is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱1,960,108.84. Status: Reported complete (DPWH). Contractor on record: PAR BUILDERS ELECTRICAL. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,960,108.84

Progress

Reported complete (DPWH)

Start Date

January 9, 2018

Target End

April 3, 2018

5. Audit