Buildings and Facilities20II0034

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II) IN (LIGA BUILDING), LAOANG, NORTHERN SAMAR

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II) IN (LIGA BUILDING), LAOANG, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱2,934,167.92. Status: Reported complete (DPWH). Contractor on record: JBM ENGINEERS AND SUPPLY. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure: Cahayagan Seawall, Brgy. Cahayagan, Laoang, Northern Samar
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-20-0007184

₱228,687,000.00 · FY2020

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱2,934,167.92

Progress

Reported complete (DPWH)

Start Date

October 16, 2020

Target End

December 29, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.