OFF-CARRIAGEWAY IMPROVEMENT ALONG DAVAO-BUKIDNON RD- K1680+687-K1682+220

OFF-CARRIAGEWAY IMPROVEMENT ALONG DAVAO-BUKIDNON RD- K1680+687-K1682+220 is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱11,209,052.95. Status: Reported complete (DPWH). Contractor on record: TWO DEGREES CONST AND SUPPLY. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement / Rehabilitation of Flood Mitigation Facility along R. Magsaysay Ave. Outfall, Davao City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-F-20-0022111

₱47,323.00 · FY2020

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱11,209,052.95

Progress

Reported complete (DPWH)

Start Date

February 22, 2020

Target End

July 3, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.