Roads17MF0001

CONST./UPGRADING/REHABILITATION OF DRAINAGE ALONG KIDAPAWAN-ALLAH JCT. ROAD K1673+(-458)-K1673+164, TACURONG CITY, SULTAN KUDARAT

CONST./UPGRADING/REHABILITATION OF DRAINAGE ALONG KIDAPAWAN-ALLAH JCT. ROAD K1673+(-458)-K1673+164, TACURONG CITY, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱21,348,654.52. Status: Reported complete (DPWH). Contractor on record: THREE W BUILDERS INC. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱21,348,654.52

Progress

Reported complete (DPWH)

Start Date

April 21, 2017

Target End

February 10, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.