GAA 2016 DA Farm-to-Market Roads16FB0048

CONCRETING OF BONGABONG - SOLONG FMR, BRGY. BONGABONG, BRGY. SOLONG, CAMALIG, ALBAY

CONCRETING OF BONGABONG - SOLONG FMR, BRGY. BONGABONG, BRGY. SOLONG, CAMALIG, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱8,341,770.56. Status: Reported complete (DPWH). Contractor on record: ZKR CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

58 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱8,341,770.56

Progress

Reported complete (DPWH)

Start Date

May 29, 2016

Target End

August 25, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.