Buildings and Facilities22DH0070

COMPLETION OF MULTI PURPOSE COVERED COURT AT BARANGAY KANLURAN TALONGAN, CAVINTI, LAGUNA

COMPLETION OF MULTI PURPOSE COVERED COURT AT BARANGAY KANLURAN TALONGAN, CAVINTI, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱3,959,422.17. Status: Reported complete (DPWH). Contractor on record: E AGLAHI URBAN BUILDERS 44113. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Sto. Tomas, Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-22-0004964

₱630,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱3,959,422.17

Progress

Reported complete (DPWH)

Start Date

July 27, 2022

Target End

January 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.