Roads19HK0087

LOCAL INFRASTRUCTURE PROGRAM: CONCRETING OF BARANGAY ROAD-CONCRETING OF BARANGAY ROAD-BRGY. SAN ANTONIO, SIBULAN, NEGROS ORIENTAL

LOCAL INFRASTRUCTURE PROGRAM: CONCRETING OF BARANGAY ROAD-CONCRETING OF BARANGAY ROAD-BRGY. SAN ANTONIO, SIBULAN, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 2nd DEO, Negros Island Region. Reported contract value: ₱1,974,926.24. Status: Reported complete (DPWH). Contractor on record: RACCT CONST AND TRADING 35641. Figures trace to dpwh.

Negros Oriental 2nd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 35641

52 projects · ₱199.7M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE FACILITY (RIZAL BOULEVARD PARK), POBLACION BRGYS. 1 AND 4, DUMAGUETE CITY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱19.8M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY LA PAZ, BAIS CITY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2025₱9.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF TWO (2) STOREY ONE (1) SCIENCE LAB & ONE (1) ICT LABORATORY SCHOOL BUILDING AT APOLINARIO GERARDA ARNAIZ HIGH SCHOOL, MAGSUSUNOG, PAMPLONA (9.5MX23.00M)

Negros Oriental 2nd DEO, Negros Island Region

2018₱9.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF TWO (2) STOREY TWO (2) ICT LABORATORY SCHOOL BUILDING AT GOVERNOR JULIAN L. TEVES MEMORIAL HIGH SCHOOL, BAIS CITY (9.5MX23.0M)

Negros Oriental 2nd DEO, Negros Island Region

2018₱9.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF TWO(2) STOREY SIX (6) CLASSROOM SCHOOLBUILDING AT TAMPI NATIONAL HIGH SCHOOL, MABINA

Negros Oriental 2nd DEO, Negros Island Region

2016₱9.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF TWO (2) STOREY TWO (2) SCIENCE LABORATORY SCHOOL BUILDING AT GOVERNOR JULIAN L. TEVES MEMORIAL HIGH SCHOOL, CALASGAAN, BAIS CITY (9.5MX23.0M)

Negros Oriental 2nd DEO, Negros Island Region

2018₱8.9M
Reported complete (DPWH)
View all 52 projects →

4. Implementation

Contract Amount

₱1,974,926.24

Progress

Reported complete (DPWH)

Start Date

June 4, 2019

Target End

August 2, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.