Buildings and Facilities25JI0039

COMPLETION OF MULTI PURPOSE BUILDING, VILLA CORTE, OLUTANGA, ZAMBOANGA SIBUGAY

COMPLETION OF MULTI PURPOSE BUILDING, VILLA CORTE, OLUTANGA, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱2,964,175.19. Status: Past target date (DPWH On-Going). Contractor on record: KAYE-VENICE CONST. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Revetment wall) along Sibuguey River, Barangay Sta. Barbara, Imelda, Zamboanga Sibugay
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-25-0009823

₱153,160.00 · FY2025

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

60 projects · ₱345.3M total · 0 flags

4. Implementation

Contract Amount

₱2,964,175.19

Progress

Past target date (DPWH On-Going)

Start Date

July 11, 2025

Target End

October 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.