GAA 2025 SSP25FI0026

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGE FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING FACILITIES - CONSTRUCTION OF ROAD, BARANGAY TINAPIAN AND BARANGAY DOCOL, BALENO,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGE FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING FACILITIES - CONSTRUCTION OF ROAD, BARANGAY TINAPIAN AND BARANGAY DOCOL, BALENO, is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱9,700,946.91. Status: Reported complete (DPWH). Contractor on record: HAZ AND HAD CONST. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Lumbang River, Masbate City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-25-0007502

₱7,279,122.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱9,700,946.91

Progress

Reported complete (DPWH)

Start Date

March 4, 2025

Target End

May 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.