Buildings and Facilities23CL0160

REHABILITATION OF A.) MULTI-PURPOSE BUILDING, BRGY. APO-APO, CABANGAN, ZAMBALES B.) MULTI-PURPOSE BUILDING, BRGY. LAUIS, CANDELARIA, ZAMBALES

REHABILITATION OF A.) MULTI-PURPOSE BUILDING, BRGY. APO-APO, CABANGAN, ZAMBALES B.) MULTI-PURPOSE BUILDING, BRGY. LAUIS, CANDELARIA, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱6,623,370.82. Status: Past target date (DPWH On-Going). Contractor on record: SMP-JADE CONST CORP. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tanguay River Flood Control Structure, Upstream, Package 3, Barangay Sto Nino, Cabangan, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-23-0024802

₱403,985.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱6,623,370.82

Progress

Past target date (DPWH On-Going)

Start Date

December 7, 2023

Target End

March 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.