Roads16FH0083

CLUSTER III-CONST. OF ROADS IN BRGY. OBI, CARAMORAN, BRGY. TOBREJON, SAN MIGUEL AND BRGY. PANIQUIHAN, BARAS, CATANDUANES

CLUSTER III-CONST. OF ROADS IN BRGY. OBI, CARAMORAN, BRGY. TOBREJON, SAN MIGUEL AND BRGY. PANIQUIHAN, BARAS, CATANDUANES is a DPWH-tracked public work in Catanduanes DEO, Region V. Reported contract value: ₱5,939,902.52. Status: Reported complete (DPWH). Contractor on record: JR CONTRACTOR. Figures trace to dpwh.

Catanduanes DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagong Sirang Flood Control, Baras, Catanduanes
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0011469

₱5,880,000.00 · FY2017

Released to PENRO Zamboanga Modifi del Norte Expens develo Zamboa (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

50 projects · ₱308.7M total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM-LOCAL ROADS AND BRIDGES-LOCAL ROADS-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-REHAB. OF CONCRETE ROAD-REHAB/IMPVT OF BRGY. CAVINITAN TO BRGY. PAJO ROAD CONNECTING PROPOSED VIRAC TOURISM

Catanduanes DEO, Region V

2021₱27.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM - TWO (2) UNITS (7X18) SCIENCE LABORAORY AND TWO (2) UNITS (7X18) ICT LABORATORY SCHOOL BUILDING, SICMIL INTEGRATED SCHOOL, GIGMOTO, CATANDUANES

Catanduanes DEO, Region V

2018₱19.9M
Reported complete (DPWH)
No sat.

REHABILITATION/IMPROVEMENT OF BRGY. CALATAGAN TIBANG LEADING TO PROPOSED VIRAC AGRI-TOURISM SITES, VIRAC, CATANDUANES

Catanduanes DEO, Region V

2020₱15.2M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT- OFF-CARRIAGEWAY IMPROVEMENT -SECONDARY ROADS- OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION -CATANDUANES CIRCUMFERENTIAL ROAD K0008+000 -K0008+726, K0008+780 -K0008+807, K0008+984 - K0010+625

Catanduanes DEO, Region V

2022₱14.7M
Reported complete (DPWH)
No sat.

REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE, JCT. BATO-BARAS ROAD K0013+380-K0013+389 & K0013+700-K0014+000, BATO, CATANDUANES

Catanduanes DEO, Region V

2018₱13.2M
Reported complete (DPWH)
No sat.

EMERGENCY REPAIR/MAINTENANCE OF CATANDUANES CIRCUMFERENTIAL ROAD SAN ANDRES-VIRAC ROAD SECTION, LICTIN, SAN ANDRES, CATANDUANES (K0190+490-K0192+000) AT INT. SECTION

Catanduanes DEO, Region V

2016₱11.8M
Reported complete (DPWH)
View all 50 projects →

4. Implementation

Contract Amount

₱5,939,902.52

Progress

Reported complete (DPWH)

Start Date

March 5, 2017

Target End

June 2, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.