CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. SAN ISIDRO, LAUR, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱4,365,779.25. Status: Reported complete (DPWH). Contractor on record: F L REGUYAL CONST CORP. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-19-0011919

₱716,783.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,365,779.25

Progress

Reported complete (DPWH)

Start Date

July 4, 2019

Target End

September 16, 2019