Roads21JD0004

CONSTRUCTION/UPGRADING/RAHABILITATION OF DRAINAGE ALONG NATIONAL ROADS ILAYA-ISIS-POLANCO ROAD K1817+587

CONSTRUCTION/UPGRADING/RAHABILITATION OF DRAINAGE ALONG NATIONAL ROADS ILAYA-ISIS-POLANCO ROAD K1817+587 is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱2,854,325.47. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱1,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control structure along Right Bank of Talinga River (downstream), Sindangan, Zamboanga del Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱392,621,000.00 · FY2021

Released to Batangas 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,854,325.47

Progress

Reported complete (DPWH)

Start Date

March 25, 2021

Target End

December 2, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.