Flood Control and Drainage20OH0035

LOCAL PROGRAM-CONST./REPAIR/REHAB./IMPV'T. OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-FLOOD

LOCAL PROGRAM-CONST./REPAIR/REHAB./IMPV'T. OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-FLOOD is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱47,227,180.00. Status: Reported complete (DPWH). Contractor on record: TRIPLE 8 CONST. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 76%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Banga River,Brgy. Malaya, Banga, South Cotabato
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-20-0021678

₱50,000,000.00 · FY2020

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

276 projects · ₱13.4B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF REVETMENT ALONG MARIBLO CREEK, STA. 0+010.000 TO STA. 0+524.458 (LEFT AND RIGHT RIVER BANK), QUEZON CITY

Flood Control Management Cluster, Central Office

2021₱195.0M
Reported complete (DPWH)
No sat.

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADSBACOOR - DASMARIÑAS NATIONAL RD. - K0028 + 215 - K0028 + 404, K0029 + 204 - K0029 + 780, K0029 + 822 - K0030 + 675, K0030 + 716 - K0030 + 1002, K0031 + 015 - K0031 + 609

Region IV-A, Region IV-A

2023₱154.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION OF CAMP AGUINALDO ROAD NETWORK, PACKAGE A, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT ALONG DARIO CREEK, STA. 0+020.000 TO STA. 0+351.894 (LEFT AND RIGHT RIVER BANK), QUEZON CITY

Flood Control Management Cluster, Central Office

2021₱135.7M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONSTRUCTION OF OPEN UNIVERSITY SYSTEM BUILDING IN POLYTECHNIC UNIVERSITY OF THE PHILIPPINES (PUP) PHASE II AT PUP A. MABINI CAMPUS, STA. MESA, MANILA

South Manila DEO, National Capital Region

2023₱111.0M
Reported complete (DPWH)

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, FLOOD CONTROL AND DRAINAGE, FLOOD CONTROL STRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, BRGY. BUHAY NA TUBIG, PHASE IV, IMUS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2019₱99.0M
Reported complete (DPWH)
View all 276 projects →

4. Implementation

Contract Amount

₱47,227,180.00

Progress

Reported complete (DPWH)

Start Date

December 3, 2020

Target End

June 30, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.