GAA 2024 OO-124I00057

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (S00223LT) - K1014+000 - K1014+727, K1016+865 - K1017+000, K1017+085 - K1018+620

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (S00223LT) - K1014+000 - K1014+727, K1016+865 - K1017+000, K1017+085 - K1018+620 is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱217,478,000.00. Status: Past target date (DPWH On-Going). Contractor on record: QM BUILDERS. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

769 projects · ₱47.1B total · 123 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MATALAO -BRGY. MANLAPAY, DUMANJUG, CEBU

Region VII, Region VII

2025₱359.4M
Past target date (DPWH On-Going)
No sat.

CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), POBLACION, DUMANJUG, CEBU

Region VII, Region VII

2024₱313.6M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONST.OF NATIONAL ROADS WITH SLIPS, SLOPE, COLLAPSE, AND LANDSLIDE, SECONDARY ROADS,CEBU TOLEDO WHARF ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING

Region VII, Region VII

2016₱295.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, ROAD CONCRETING OF SRP BACK ROAD (PHASE III)

Region VII, Region VII

2023₱289.4M
Past target date (DPWH On-Going)
No sat.

MF0-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES , SECONDARY ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING,) K0011+237-K0013+245, K0016+50

Region VII, Region VII

2017₱289.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONST. OF ROAD, BARANGAY LIBO-BARANGAY GUIBANGCO-AN, SIBONGA, CEBU PHASE 2

Region VII, Region VII

2025₱283.7M
Past target date (DPWH On-Going)
View all 769 projects →

4. Implementation

Contract Amount

₱217,478,000.00

Progress

Past target date (DPWH On-Going)

Start Date

April 5, 2024

Target End

April 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.