Roads23AA0459

CONCRETING OF BRGY. MALAMPA FMR, BRGY. MALAMPA, VINTAR, ILOCOS NORTE

CONCRETING OF BRGY. MALAMPA FMR, BRGY. MALAMPA, VINTAR, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱9,552,686.30. Status: Past target date (DPWH On-Going). Contractor on record: ZEDIK BUILDERS. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bacarra River, Brgy. 1 Santa Rita, Bacarra, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-23-0020099

₱390,246.00 · FY2023

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,552,686.30

Progress

Past target date (DPWH On-Going)

Start Date

July 11, 2023

Target End

November 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.