Roads22PJ0001

22PJ0001: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - BUTAC-MONGGAYANG ROAD CONN

22PJ0001: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - BUTAC-MONGGAYANG ROAD CONN is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱19,622,540.00. Status: Reported complete (DPWH). Contractor on record: CJ ALCONS CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Magat River, Sta. 39 + 563 - Sta. 40 + 975, Sta. 41 + 668 - Sta. 41 + 706, San Juan and Calupaan, Alfonso Lista, Ifugao
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0012326

₱-19,851,366.00 · FY2022

Released to Leyte Normal University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

45 projects · ₱638.3M total · 0 flags

Other projects by this contractor

No sat.

25PJ0033: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF BRIDGE, (MINANGA) ALONG STA. MARIA - SAN MARCOS, ALFONSO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱77.2M
Past target date (DPWH On-Going)
No sat.

25PJ0028: FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, STA. 52+500 - STA. 53+400 (L/S), ALIMIT, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱75.6M
Past target date (DPWH On-Going)
No sat.

24PJ0042-CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF MINANGNGA BRIDGE, AL

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱34.3M
Reported complete (DPWH)
No sat.

23PJ0039: CONVERGENCE AND SPECIALSUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS(SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADSCONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES-CONSTRUCTION OFROAD, AWAN-IGID, VIEWPO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱31.4M
Reported complete (DPWH)
No sat.

LAGAWE-BOLIWONG-ABINUAN ROAD LEADING TO INCHANG FALLS LAGAWE, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2020₱29.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF LAMUT FLOOD CONTROL, LAMUT, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2020₱26.9M
Reported complete (DPWH)
View all 45 projects →

4. Implementation

Contract Amount

₱19,622,540.00

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

September 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.