Construction of Revetment23OC0088

Construction of Revetment near Salvador Bridge (Upstream Side), Barangay San Isidro, Parañaque City, Metro Manila

Construction of Revetment near Salvador Bridge (Upstream Side), Barangay San Isidro, Parañaque City, Metro Manila is a DPWH-tracked public work in CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region. Reported contract value: ₱48,999,076.10. Status: Reported complete (DPWH). Contractor on record: EURO CONST AND SUPPLY FORMERLY: EURO CONST AND TRADING. Figures trace to sumbong.

CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱36,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control, Brgy. Little Baguio, San Juan City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0024870

₱60,191.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,076.10

Progress

Reported complete (DPWH)

Start Date

May 23, 2023

Target End

March 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.