Roads22IB0025

OFF-CARRIAGEWAY IMPROVEMEN SECONDARY ROADS, BORONGAN - GUIUAN ROAD K0924+(-289)- K0924+711, BORONGAN, EASTERN SAMAR

OFF-CARRIAGEWAY IMPROVEMEN SECONDARY ROADS, BORONGAN - GUIUAN ROAD K0924+(-289)- K0924+711, BORONGAN, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱9,702,000.00. Status: Reported complete (DPWH). Contractor on record: DRAGON CONST 48354. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Brgy. Cabong Flood Control, Brgy. Cabong, Borongan City, Eastern Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0015779

₱9,234,991.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,702,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2022

Target End

June 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.