Buildings and Facilities25OB0308

CONSTRUCTION (COMPLETION) OF NACIDA INCUBATOR FACILITY INCLUDING SITE DEVELOPMENT, BARANGAY CONCEPCION DOS, PHASE IV MARIKINA CITY

CONSTRUCTION (COMPLETION) OF NACIDA INCUBATOR FACILITY INCLUDING SITE DEVELOPMENT, BARANGAY CONCEPCION DOS, PHASE IV MARIKINA CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱94,569,345.07. Status: Reported complete (DPWH). Contractor on record: JK2CS CONST AND TRADING CORP. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0011891

₱631,595.00 · FY2025

Released to Regional Office - XI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱94,569,345.07

Progress

Reported complete (DPWH)

Start Date

May 20, 2025

Target End

December 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.