Buildings and Facilities23CN0042

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), SO. CASTILLO, SABANG, BALER, AURORA

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), SO. CASTILLO, SABANG, BALER, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱2,970,000.00. Status: Reported complete (DPWH). Contractor on record: VANMARVIL CONST 19224. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, So. Setan, Brgy. Calabuanan, Baler, Aurora
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱2,970,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2023

Target End

May 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.