Roads24CL0022

INSTALLATION/APPLICATION OF SIGNAGE AND PAVEMENT MARKINGS ALONG OLONGGAPO-BUGALLON ROAD-K0234+200-K0234+800, BALOGANON, MASINLOC, ZAMBALES

INSTALLATION/APPLICATION OF SIGNAGE AND PAVEMENT MARKINGS ALONG OLONGGAPO-BUGALLON ROAD-K0234+200-K0234+800, BALOGANON, MASINLOC, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱910,799.06. Status: Reported complete (DPWH). Contractor on record: JCOB CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Tapuac - Sta Maria River, Masinloc, Zambales ( Phase 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-24-0008180

₱217,502.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱910,799.06

Progress

Reported complete (DPWH)

Start Date

May 21, 2024

Target End

July 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.