Flood Control and Drainage24IC0078

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, PHASE 2, BRGY. BALUD TO BRGY. STA. ELENA, TANAUAN, LEYTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, PHASE 2, BRGY. BALUD TO BRGY. STA. ELENA, TANAUAN, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱144,646,923.03. Status: Past target date (DPWH On-Going). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Mainit River, Barangay Cavite, Alangalang, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-24-0004269

₱6,384,568.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 0 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱144,646,923.03

Progress

Past target date (DPWH On-Going)

Start Date

August 21, 2024

Target End

July 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.