GAA 2025 SSP25OB0374

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, BARANGAY BAGONG SILANG, MANDALUYONG CITY, PHASE

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, BARANGAY BAGONG SILANG, MANDALUYONG CITY, PHASE is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱19,403,334.90. Status: Past target date (DPWH On-Going). Contractor on record: VIRAC NRC CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0011891

₱631,595.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱19,403,334.90

Progress

Past target date (DPWH On-Going)

Start Date

May 20, 2025

Target End

January 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.