Buildings and Facilities18GH0020

COMPLETION OF COVERED COURT, BRGY. TABUNAN, LEMERY, ILOILO

COMPLETION OF COVERED COURT, BRGY. TABUNAN, LEMERY, ILOILO is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱1,479,999.29. Status: Reported complete (DPWH). Contractor on record: PITONG BUILDERS. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,479,999.29

Progress

Reported complete (DPWH)

Start Date

April 26, 2018

Target End

July 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.