Water Provision and Storage21FI0054

CLUSTER I - CONSTRUCTION OF RAINWATER COLLECTOR (RWCS) AT MASBATE CITY; A. NICOLAS DANAO ES, MASBATE CITY; B. FLORENTINO C. VERSOZA ES, MASBATE CITY

CLUSTER I - CONSTRUCTION OF RAINWATER COLLECTOR (RWCS) AT MASBATE CITY; A. NICOLAS DANAO ES, MASBATE CITY; B. FLORENTINO C. VERSOZA ES, MASBATE CITY is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱614,008.35. Status: Reported complete (DPWH). Contractor on record: 3R3M CONST AND SUPPLY CORP FORMERLY: 3R3M CONST AND SUPPLY 45410. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lumbang River Flood Control Masbate City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱407,327,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 45410

68 projects · ₱871.3M total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BITO RIVER (DOWNSTREAM), BRGY. CORBADA, SAN FERNANDO, MASBATE.

Masbate 1st DEO, Region V

2024₱49.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF CANOMAY FLOOD CONTROL, BARANGAY CANOMAY, DIMASALANG, MASBATE

Masbate 3rd DEO, Region V

2024₱48.9M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORE PROTECTION STRUCTURE, LAGUNDI, BARANGAY BURGOS, BATUAN, MASBATE.

Masbate 1st DEO, Region V

2025₱47.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - JCT. TAWAD-BALUD ROAD (S00023MT) K0039+670 - K0039+812, K0039+882 - K0040+019

Masbate 2nd DEO, Region V

2025₱38.4M
Past target date (DPWH On-Going)
No sat.

OO1: NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS, BUENAVISTA- KAWAYAN RD- K0050+729- K0051+400

Masbate 3rd DEO, Region V

2024₱34.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 3STY9CL, AMANCIO AGUILAR ELEMENTARY SCHOOL, MASBATE CITY, MASBATE

Masbate 2nd DEO, Region V

2023₱30.2M
Reported complete (DPWH)
View all 68 projects →

4. Implementation

Contract Amount

₱614,008.35

Progress

Reported complete (DPWH)

Start Date

September 28, 2022

Target End

October 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.