Roads21AB0008

REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES - TERTIARY ROADS, BATAC-PINILI VIA MAIPALIG RD - K0474+795 - K0474+827, K0480+000 - K0480+124, K0481+045 - K0481+177, K0487+010 - K0487+050, K0487+375 - K0487+405

REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES - TERTIARY ROADS, BATAC-PINILI VIA MAIPALIG RD - K0474+795 - K0474+827, K0480+000 - K0480+124, K0481+045 - K0481+177, K0487+010 - K0487+050, K0487+375 - K0487+405 is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱24,990,000.00. Status: Reported complete (DPWH). Contractor on record: MEGAPOLITAN BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱1,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Bongo River, Brgy. Peralta, Dingras, Ilocos Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-21-0011670

₱9,036,599.00 · FY2021

Released to Southern Leyte State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

354 projects · ₱7.2B total · 6 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SRIP AND ITS APPURTENANT STRUCTURE, CABANGARAN SRIP, BARANGAY CABANGARAN, VINTAR, ILOCOS NORTE

Region I, Region I

2025₱149.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 2, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 1, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, BARANGAY MABALENG, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱122.7M
Past target date (DPWH On-Going)

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF QUIAOIT RIVER DIVERSION CANAL, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱115.8M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF SWIP, BARANGAY CAMANDINGAN, CITY OF BATAC, ILOCOS NORTE

Region I, Region I

2025₱112.3M
Past target date (DPWH On-Going)
View all 354 projects →

4. Implementation

Contract Amount

₱24,990,000.00

Progress

Reported complete (DPWH)

Start Date

February 15, 2021

Target End

November 4, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.