Buildings and Facilities25OC0081

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, J.P RIZAL, BARANGAY SANTO NIÑO,PARAÑAQUE CITY, METRO MANILA

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, J.P RIZAL, BARANGAY SANTO NIÑO,PARAÑAQUE CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱9,701,912.07. Status: Past target date (DPWH On-Going). Contractor on record: MCORR CONST. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Don Galo River, Barangay Don Galo, Parañaque City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-25-0017963

₱0.00 · FY2025

Released to Regional Office - IVB (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

12 projects · ₱138.8M total · 0 flags

4. Implementation

Contract Amount

₱9,701,912.07

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

August 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.