BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PANCIAO, MANJUYOD, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱1,974,362.90. Status: Reported complete (DPWH). Contractor on record: E F V CONST SERVICES. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱17,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Tinaogan, Bindoy, Negros Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-25-0016891

₱1,680,345.00 · FY2025

Released to Regional Office - VIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

7 projects · ₱42.3M total · 0 flags

Other projects by this contractor

No sat.

CONCRETING OF BRGY. SALONG SAC-SAC FMR, BRGY. SALONG SAC-SAC, BINDOY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱14.9M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF BARANGAY SANDAYAO TO BARANGAY TACPAO ROAD CONNECTING JCT. DUMAQUE

Negros Oriental 1st DEO, Negros Island Region

2025₱14.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TIGUIB, AYUNGON, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱4.9M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BUTONG, MANJUYOD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱2.0M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAMPUYO, MANJUYOD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱2.0M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SALONG, BINDOY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱2.0M
Reported complete (DPWH)
View all 7 projects →

4. Implementation

Contract Amount

₱1,974,362.90

Progress

Reported complete (DPWH)

Start Date

March 7, 2025

Target End

May 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.