Buildings and Facilities18HD0102

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MAÑO, SAN REMEGIO, CEBU

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MAÑO, SAN REMEGIO, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱2,821,214.73. Status: Reported complete (DPWH). Contractor on record: DINAH RBS CONST AND SUPPLY INC FORMERLY: DINAH JANE CONST AND SUPPLY. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Alegria Seawall, Alegria, Cebu
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Cebu 4th DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

4. Implementation

Contract Amount

₱2,821,214.73

Progress

Reported complete (DPWH)

Start Date

March 13, 2018

Target End

May 21, 2018

5. Audit