Buildings and Facilities17HE0082

COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY SANGAT, SAN FERNANDO, CEBU

COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY SANGAT, SAN FERNANDO, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱479,655.00. Status: Reported complete (DPWH). Contractor on record: JANUARY BUILDERS. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control of Bangon Bridge (Downstream), Poblacion, Cebu
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Cebu 1st DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱479,655.00

Progress

Reported complete (DPWH)

Start Date

May 19, 2017

Target End

June 17, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.