Roads23CJ0090

NETWORK DEVELOPMENT PROGRAM ROAD WIDENING STA. IGNACIA-GERONA-PURA-GUIMBA RD (S05056LZ) - CHAINAGE 19255 - CHAINAGE 21115, CHAINAGE 21795 - CHAINAGE 22211

NETWORK DEVELOPMENT PROGRAM ROAD WIDENING STA. IGNACIA-GERONA-PURA-GUIMBA RD (S05056LZ) - CHAINAGE 19255 - CHAINAGE 21115, CHAINAGE 21795 - CHAINAGE 22211 is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱44,374,400.00. Status: Reported complete (DPWH). Contractor on record: BIG BERTHA CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-23-002689

₱687,586,680.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱44,374,400.00

Progress

Reported complete (DPWH)

Start Date

March 23, 2023

Target End

December 2, 2023

5. Audit