Buildings and Facilities19FB0123

LOCAL INFRASTRUCTURE PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. EM'S BARRIO 1 (POBLACION), LEGAZPI CITY, ALBAY

LOCAL INFRASTRUCTURE PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. EM'S BARRIO 1 (POBLACION), LEGAZPI CITY, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱4,831,291.23. Status: Reported complete (DPWH). Contractor on record: DN'D CONST AND DEVELOPMENT. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

62 projects · ₱1.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE TRAINING AND INSTRUCTION FACILITY/MEETINGS, INCENTIVES, CONFERENCES FOR EDUCATION AND S

Region V, Region V

2024₱147.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0534+630.00-K0537+834.90; K0537+850.40-K0538+400.00, DARAGA, ALBAY 2ND LEGISLATIVE DISTRICT

Region V, Region V

2019₱126.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROAD, JCT. NATO-SABANG COASTAL ROAD, NATO SECTION, CAMARINES SUR PACKAGE B, SAGNAY, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF STA. CRUZ - PINTOR

Albay 3rd DEO, Region V

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF STA. CRUZ - PINTOR

Albay 3rd DEO, Region V

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BRGY. ALNAY, POLANG

Albay 3rd DEO, Region V

2025₱74.9M
Past target date (DPWH On-Going)
View all 62 projects →

4. Implementation

Contract Amount

₱4,831,291.23

Progress

Reported complete (DPWH)

Start Date

June 26, 2019

Target End

October 23, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.