Flood Control and Drainage21BJ0009

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF MARANG RIVER FLOOD CONTROL STRUCTURES, BITNONG SECTION, DUPAX DEL NORTE, NUEVA VIZCAYA

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF MARANG RIVER FLOOD CONTROL STRUCTURES, BITNONG SECTION, DUPAX DEL NORTE, NUEVA VIZCAYA is a DPWH-tracked public work in Nueva Vizcaya 2nd DEO, Region II. Reported contract value: ₱48,999,644.14. Status: Reported complete (DPWH). Contractor on record: BRG CONST 21931. Figures trace to dpwh.

Nueva Vizcaya 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Marang River Flood Control Structures, Bitnong Section, Nueva Vizcaya
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-21-0010533

₱263,769.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 21931

73 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. CRUZ RIVER, SITIO PALTUG, BARANGAY SAN F

Nueva Vizcaya 2nd DEO, Region II

2025₱93.7M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. CRUZ RIVER, BARANGAY GABUT, DUPAX DEL S

Nueva Vizcaya 2nd DEO, Region II

2025₱93.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD STRUCTURE ALONG TUBO RIVER, BARANGAY PUDI, KASIBU, NUEVA VIZCAYA

Nueva Vizcaya 2nd DEO, Region II

2025₱88.9M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, DUPAX DEL SUR BYPASS, NUEVA VIZCAYA, DUPAX DEL SUR, NUEVA VIZCAYA

Nueva Vizcaya 2nd DEO, Region II

2023₱87.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION CONSTRUCTION UPGRADING REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS PRIMARY ROADS POBLACION, BAMBANG, NUEVA VIZCAYA SECTION 1 : STA. 0 + 000 STA. 0 + 533.85, SECTION 2: S

Nueva Vizcaya DEO, Region II

2023₱77.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM CONSTRUCTION OF STA. FE RIVER FLOOD CONTROL STRUCTURES, NAGCUARTELAN SECTION, ARITAO, NUEVA VIZCAYA

Nueva Vizcaya 2nd DEO, Region II

2021₱49.0M
Reported complete (DPWH)
View all 73 projects →

4. Implementation

Contract Amount

₱48,999,644.14

Progress

Reported complete (DPWH)

Start Date

February 12, 2021

Target End

October 19, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.