Roads21DF0053

LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMLOCAL ROADS AND BRIDGESLOCAL ROADSREHABILITATION OF LOCAL ROAD, BARANGAY BANABA CERCA, INDANG; REHABILITATION OF LOCAL ROAD, BARANGAY BANCOD, INDANG AND REHABILITATION OF LOCAL ROAD, BARANGAY MATAAS NA LUPA

LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMLOCAL ROADS AND BRIDGESLOCAL ROADSREHABILITATION OF LOCAL ROAD, BARANGAY BANABA CERCA, INDANG; REHABILITATION OF LOCAL ROAD, BARANGAY BANCOD, INDANG AND REHABILITATION OF LOCAL ROAD, BARANGAY MATAAS NA LUPA is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱14,080,068.59. Status: Reported complete (DPWH). Contractor on record: J M MALIGAYA CONST CORP FORMERLY: J M MALIGAYA CONST. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures and Drainage Systems along Cavite-Batangas Road, K0044 + 800 - K0045 + 100 with exceptions, Silang, Cavite
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱1,250,000,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

54 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM,NETWORK DEVELOPMENT, CONSTRUCTION OF MISSING LINKS/NEW ROADS-GENERALAGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), AMADEO SECTION,CAVITE

Cavite 1st DEO, Region IV-A

2019₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADSGENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD(EAST - WEST ROAD), INDANG - WEST SECTION, CAVITE

Region IV-A, Region IV-A

2023₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST-WEST ROAD), INDANG-WEST SECTION, CAVITE

Region IV-A, Region IV-A

2022₱95.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENTCONSTRUCTION OF BY-PASS AND DIVERSION ROADSDASMARINAS - GENERAL TRIAS - TANZA (PUNTA - BAGTAS SECTION), TANZA, CAVITE

Cavite 1st DEO, Region IV-A

2025₱95.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION OF INDANG-CABUCO-NAIC DIVERSION ROAD, TRECE MARTIRES CITY

Cavite 1st DEO, Region IV-A

2020₱94.6M
Reported complete (DPWH)
No sat.

LOCAL PROGRAMCONST. / REPAIR / REHAB. / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTSLOCAL ROADS AND BRIDGESLOCAL BRIDGECONSTRUCTION OF SAHUD ULAN BRIDGE ALONG SAHUD ULAN-TRES CRUSES-TMC ROAD, BARANGAY TRES CRUSES SECTION, TANZA,

Cavite 1st DEO, Region IV-A

2021₱93.6M
Reported complete (DPWH)
View all 54 projects →

4. Implementation

Contract Amount

₱14,080,068.59

Progress

Reported complete (DPWH)

Start Date

February 7, 2021

Target End

May 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.