Construction of Flood Mitigation Structure24AF0161

Construction of Flood Control Structure along Aringay River Basin, Barangay San Juan East, Aringay, La Union (Phase 2)

Construction of Flood Control Structure along Aringay River Basin, Barangay San Juan East, Aringay, La Union (Phase 2) is a DPWH-tracked public work in ARINGAY (LA UNION), LA UNION, Region I. Reported contract value: ₱28,943,409.41. Status: Reported complete (DPWH). Contractor on record: T2B3 BUILDERS AND SUPPLIES CORP / RPV RED MOUNTAIN KONSTRUCT INC. Figures trace to sumbong.

ARINGAY (LA UNION), LA UNION, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aringay River Basin, Barangay Cares, Pugo, La Union
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007428

₱1,468,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007429

₱136,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0001848

₱66,413.00 · FY2024

Source

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0017565

₱12,389,084.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱28,943,409.41

Progress

Reported complete (DPWH)

Start Date

August 13, 2024

Target End

February 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.