Roads22PA0019

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, ABRA-KALINGA ROAD-K0439+100-K0439+170

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, ABRA-KALINGA ROAD-K0439+100-K0439+170 is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱48,997,257.29. Status: Reported complete (DPWH). Contractor on record: PHESCO INC 145. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱42,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Banglolao-Labon Flood Control Structure, Bucay, Abra
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-22-0014818

₱8,046,838.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

342 projects · ₱29.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES SOOT BRIDGE (B00989LZ) ALONG ABRA - ILOCOS NORTE ROAD

Cordillera Administrative Region, Cordillera Administrative Region

2020₱530.8M
Reported complete (DPWH)
No sat.

CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS GOV. BADO DANGWA NATIONAL ROAD (1) K0342 +

Cordillera Administrative Region, Cordillera Administrative Region

2021₱492.1M
Reported complete (DPWH)
No sat.

ROCKFALL NETTING INCLUDING IMPROVEMENT OF CRITICAL INTERSECTION AT JCT. SHRINE HILLS ALONG DAVAO CITY DIVERSION ROAD, MATINA CROSSING, DAVAO CITY

Region XI, Region XI

2021₱333.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BENGUET - NUEVA VIZCAYA ROADKO254+(-372) - KO281+800BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2021₱289.5M
Reported complete (DPWH)
No sat.

MT PROV - CAGAYAN VIA TABUK - ENRILE RD, K0406+453 - KO406+692SADANGA, MT. PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINTENANCE OF ROAD:ASPHALT OVERLAY/ITEM 304-A (SLURRY SURFACE TREATMENT 12MM) WITH CORRECTION - BENGUET - NUEVA VIZCAYA ROAD, K

Cordillera Administrative Region, Cordillera Administrative Region

2021₱289.5M
Reported complete (DPWH)
View all 342 projects →

4. Implementation

Contract Amount

₱48,997,257.29

Progress

Reported complete (DPWH)

Start Date

March 4, 2022

Target End

September 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.