Roads17RF0080

CONCRETING OF BRGY. GUBA TO TAGBINO FMR, BRGYS. GUBA AND TAGBINO, VALLEHERMOSO, NEGROS ORIENTAL

CONCRETING OF BRGY. GUBA TO TAGBINO FMR, BRGYS. GUBA AND TAGBINO, VALLEHERMOSO, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱6,902,454.05. Status: Reported complete (DPWH). Contractor on record: BACOLOD RED DRAGON CONST INC. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tampocon Flood Control along Dumaguete North Road, Brgy. Tampocon I, Ayungon, Negros Oriental
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-17-0012607

₱-4,999.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱6,902,454.05

Progress

Reported complete (DPWH)

Start Date

January 3, 2018

Target End

April 2, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.