GAA 2016 MFO-216NB0004

IMPROV'T/REHAB. OF ANDANAN RIVER CONTROL (PHASE III) STA.0+000-0+800, BAYUGAN CITY, AGUSAN DEL SUR

IMPROV'T/REHAB. OF ANDANAN RIVER CONTROL (PHASE III) STA.0+000-0+800, BAYUGAN CITY, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱45,715,626.74. Status: Reported complete (DPWH). Contractor on record: CM TAN CONST. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 76%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Telaje Flood Control, Tandag City, Surigao del Sur
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Agency-level releases for FY2016, not tied to this contract

Agusan del Sur 1st DEO · SARO 2,111 (₱111,347,307,043.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱45,715,626.74

Progress

Reported complete (DPWH)

Start Date

March 28, 2016

Target End

September 23, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.