Buildings and Facilities16HC0006

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF COVERED COURT, BARANGAY CALANGAMAN, UBAY, BOHOL

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF COVERED COURT, BARANGAY CALANGAMAN, UBAY, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱2,277,000.00. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,277,000.00

Progress

Reported complete (DPWH)

Start Date

March 21, 2016

Target End

June 3, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.